Contract No. DC/2006/02 - Yuen Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai Drainage Improvements Drainage Services Department BLACK & VEATCH Chit Cheung Construction Co. Ltd.
Project Description Project Profile Environmental Permit EM&A Location EM&A Reports Landscape & Visual Mitigation Plan
//Project Description
click to enlarge
Important Note:
Contract No. DC/2006/02 comprises construction of secondary Channels KT2 and KT15 but only Channel KT15 is a Designated Project and covered by Environmental Permit.

This Website contains environmental information only for Channel KT15 under the current issue of Environmental Permit No. EP-231/2005/A. There is another secondary Channel KT14A, apart from Channel KT15, which is also covered by the said Environmental Permit. However, Channel KT14A  is being constructed under another DSD's Contract No.DC/2007/17 that has commenced on 31 December 2007 and scheduled to complete by end of 2010. The website address for KT14A is www.dc200717.com


Holder of Environmental Permit (EP) : Drainage Services Department
Consultant : Black & Veatch HK Ltd.
Contractor : Chit Cheung Construction Co., Ltd.
Location of Channel KT15 : Pat Heung , New Territories (see location plan)
Current Issue of EP : EP-231/2005/A dated 27 April 2007
Contract Sum : HK $ 123.9M (including both Channels KT2 and KT15)
Contract Period : 32 months
Contract Award Date : 21 March 2007
Contract Commencement Date : 30 March 2007
Anticipated Completion Date : 31 December 2009

» Scope of Channel KT15 and Associated Works
  1. construction of about 0.8 km of secondary drainage channel;
  2. construction of DSD maintenance access;
  3. construction of public access road with footpath;
  4. provisioning and re-provisioning of vehicular/ pedestrian crossings;
  5. associated ancillary works; and
  6. construction of a temporary vehicular access in Portion 5A1 of the Site for vehicular access from Kam Sheung Road to Lot Nos. 398RP, 395 in DD106 which are adjacent to the Site.


» Contact details of responsible persons

  Name Telephone Fax
Environmental Protection Dept.

Environmental Protection Officer(Strategic Assessment)
Environmental Protection Officer (Regional Office - North)


Ms. Sally W S Fung
Mr. Eric T S Ho


2835 2085
2158 5825


2591 0558
2650 6033
Permit Holder
Drainage Services Department
Project Engineer


Mr. P Cheng


2594 7262


2827 8526
Consultant
Black & Veatch HK Ltd.
Project Manager
Engineer's Representative (SRE)
Resident Engineer


Mr. Eric K I Lo
Mr. Clive C H Cheng
Mr. Albert Y S Yeu


2601 1000
2478 9161
2478 9161


2601 3988
2478 9396
2478 9396
Independent Environmental Checker
ENSR Asia (HK) Ltd.
Independent Environmental Checker


Mr. Y T Tang


2893 1551


2891 0305
Contractor
Chit Cheung Construction Co., Ltd.
Project Manager
Site Agent


Mr. Lawrence C L Tse
Mr. M K Ng


2403 1118
2479 1360


2403 1162
2479 1965
Environmental Team
Action-United Environmental Services & Consulting
Project Team Director
Environmental Team Leader


Mr. T W Tam
Mr. Ken K C Wong


2959 6059
2959 6059


2959 6079
2059 6079

DC/2006/02, Yuen Long Drainage, EP-231/2005/A and Channel KT15